NEC Chapter 6 — Special Equipment overview

Chapter 6 — Special Equipment

PV, EV, signs, welders, elevators, pools, IT rooms, fire pumps — gear with its own rules.

10
Major Articles
15
Quiz Questions
20
Visual Examples
🪧

Art. 600 — Electric Signs & Outline Lighting

  • 600.5(A)Provide a dedicated branch circuit (typically 20A, 120V) to each sign/outline lighting system—no other loads permitted.
  • 600.6(A)(1)A readily accessible disconnect must be within sight of the sign or outline lighting system unless exceptions apply.
  • 600.3All sign equipment must be listed/identified and installed per the label and instructions (mounting, conductors, environmental limits).
  • 300/600 blendFollow Chapter 3 wiring method rules; use wet/damp-rated fittings where exposed to weather.
  • Grounding/BondingBond metallic sign enclosures and raceways; maintain a low-impedance fault path back to the source.
EXAM TRAP
If it’s a sign circuit, it’s dedicated. Don’t add receptacles/lighting. Disconnect must be within sight unless a permitted exception is met.
Sign disconnect within sight
Local disconnect: labeled and readily accessible.
Listed sign power supply
Use listed components and follow markings.
🛗

Art. 620 — Elevators, Escalators, Platform Lifts

  • 620.51Means for disconnecting with lock-open capability for driving machines, controllers, and machinery spaces.
  • 620.22Separate lighting/receptacle circuits from power/drive circuits per 620; don't mix them.
  • 620.53Car-light/receptacle circuits often require GFCI and dedicated supply; check adopted cycle details.
  • 620.37/620.21Use wiring methods identified for the spaces (hoistway, machinery room, pit). Moisture, movement, and service access matter.
  • LabelingControllers and disconnects must be labeled clearly; AHJ will look for consistency with drawings and O&M docs.
RULE OF THUMB
Keep elevator car lights/recepts separate from drive power. Disconnects must be lockable and located where required.
Elevator machine room disconnect
Lockable disconnect within the room.
Controller cabinet with labeling
Follow controller labeling and 620 specifics.
🚗

Art. 625 — Electric Vehicle Supply Equipment (EVSE)

  • 625.41GFCI/ground-fault protection often integral to EVSE; understand how upstream protection interacts.
  • 625.42EVSE is a continuous load — size conductors and OCPD at 125% of nameplate.
  • 625.44/625.46Follow rules for cord-and-plug vs hard-wired EVSE, cord lengths, and mounting heights.
  • LabelingPlacards for maximum output/rating and circuit requirements help techs and inspectors verify compliance.
  • VentilationSome legacy equipment requires ventilation; modern listed EVSE may waive it—check the listing.
NEC REFERENCE
Treat EVSE as continuous. Example: 40A nameplate → 50A breaker (125%) with conductors to match.
Wall-mounted EVSE
Confirm continuous-load sizing and GFCI behavior.
EVSE nameplate close-up
Size to nameplate × 125%.
🧰

Art. 630 — Electric Welders

  • Duty CycleWelder input current depends on duty cycle; use 630 tables/notes instead of generic branch rules.
  • OCPDOCPD/conductor sizing can be smaller or larger than standard due to 630 multipliers—follow the table math.
  • ReceptaclesUse the correct configuration/rating; verify cord caps match receptacle/branch rating.
  • Feeder ImpactGroups of welders can be diversified per 630; don't oversize blindly.
  • NameplateWhen in doubt, the nameplate + Article 630 drive the design—don't 'average' ratings.
TABLE
Quick Sheet — Duty Cycle Multipliers
Duty CycleMultiplier (≈)Notes
100%1.00×Rated input current
60%0.80×Common shop welder example
50%0.71×Use Article 630 tables
30%0.55×Use Article 630 tables
Use Article 630 nameplate + tables for the exact multiplier, then size OCPD and conductors per 630.
Shop welder circuit
Size branch/OCPD using 630 rules.
Nameplate with duty cycle
Nameplate + 630 tables drive sizing.
🎚️

Art. 640 — Audio Systems

  • 640.9Use listed/identified equipment and cable types; support low-voltage per manufacturer and Code.
  • SeparationMaintain separation between AC power and LV audio/data as required to reduce noise and hazards.
  • Branch SizingSize power for racks/amps to nameplate; account for ventilation and heat loads.
  • GroundingBonding/grounding per manufacturer reduces hum and shock risk; avoid bootleg grounds.
  • ConnectorizationUse proper terminations (barrier strips, speakON, locking inlets) where listed; strain reliefs matter.
CHART
Audio Circuits — Common Topologies
TopologyDescription
Line-Level (balanced)XLR/TRS connections
Line-Level (unbalanced)RCA connections
Speaker-LevelAmp → speaker direct
Powered SpeakersAC + signal combined
Separate low-voltage signal from AC power where required; follow listings and 640 separation/support rules.
Audio rack power/ventilation
Ventilation and branch sizing matter.
LV cable management
Keep LV and AC separated as specified.
💻

Art. 645 — IT Equipment Rooms

  • 645.10Provide a disconnecting means for electronic equipment power (and HVAC when 645 rules are used).
  • SpacesUnderfloor plenums require plenum-rated cable; identify pathways and penetrations correctly.
  • Fire IntegrationCoordinate with fire detection/suppression; signage and EPO (if used) must be obvious.
  • Wiring MethodsSupport, secure, and protect cabling per Chapter 3—no free-air spaghetti under raised floors.
  • DocumentationLabel circuits, racks, and panel schedules; IT changes constantly—make maintenance safe and traceable.
JOBSITE HORROR STORY
A raised-floor job failed when non-plenum data cable went everywhere. Result: rip-out and replace under a production outage window.
IT room underfloor cabling
Use listed plenum/raised-floor cabling.
EPO / disconnect station
Know the shutdown sequence and labeling.
🏊

Art. 680 — Pools, Fountains, Spas

  • 680.21(A)Pool pump motors require GFCI (scope varies by edition); verify local adoption.
  • 680.26Equipotential bonding grid: bond reinforcing steel, metal components, and perimeter surfaces.
  • 680.23Wet-niche luminaires: follow listing for niches, bonding, and transformers (where used).
  • Wiring MethodsUse corrosion-resistant/wet-location wiring methods; seal fittings where required.
  • ClearancesRespect setbacks from pools for panels, receptacles, and equipment (distances vary by type).
EXAM TRAP
Equipotential bonding is a make-or-break inspection item. Bond the steel, rails, and deck surfaces properly.
Pool pump with GFCI
Expect GFCI on pump motors.
Equipotential bonding grid
Bonding ties metallic parts together.
🔋

Art. 690 — Photovoltaic Systems

  • 690.12Rapid shutdown where required; label boundaries and verify device operation.
  • 690.8(A)/(B)125% current factors for source/outputs; apply temperature correction and conduit fill derating.
  • 690.13/690.15Provide required disconnects for PV equipment and specify locations clearly.
  • LabelingPlacards at service equipment and PV points of isolation; firefighters rely on these.
  • GroundingUse listed bonding jumpers/clips for module rails and metallic raceways; continuity is critical.
NEC REFERENCE
Use 125% for PV max current, then apply conditions of use (temperature/derating). Don’t skip the label package.
PV inverter/disconnect labeling
Placards where first responders expect them.
Rooftop PV with raceways
Mind temperature and grouping corrections.
🌞

Art. 691 — Large-Scale PV (Utility-Scale)

  • ScopeApplies to utility-scale PV where engineering supervision is assumed; 691 modifies 690 for scale.
  • Docs/StudiesShort-circuit/coordination studies, relay settings, arc-flash and grounding methods are engineered.
  • EquipmentMedium-voltage collection, GIS/transformers, and switchgear—follow manufacturer and utility requirements.
  • GroundingGrounding/bonding systems are designed; soil conditions and corrosion control are addressed in the plan set.
  • Labeling/AccessAccess control, signage, and emergency response plans scale with the site footprint.
TABLE
Quick Sheet — 690 vs 691
Topic690 (Building PV)691 (Utility-Scale)
ScopeTypical building-connected PVLarge utility-scale arrays
DesignPrescriptive methods permittedEngineered systems/practices
Protection/Coord.Standard PV OCPD/labelsUtility coordination & engineered protection
DocumentationPlacards & one-linesDetailed documentation & supervision
Use 691 when the project qualifies as utility-scale; otherwise apply 690.
Utility-scale PV field
Different scale, different rule structure.
Collector station gear
Coordination and documentation drive approvals.
🚒

Art. 695 — Fire Pumps

  • 695.3Reliability: arrange normal and alternate sources for continuity—utility + generator or alternate service.
  • 695.4Feed directly to the fire pump controller with permitted taps; minimize tripping opportunities.
  • 695.5/695.6Overcurrent protection set so the pump keeps running—different than typical feeder protection.
  • RoutingProtect conductors physically (encased, MI cable, or dedicated pathways) per 695 and local amendments.
  • ControllerListed controller, signage, and lock-open isolation where required; keep the path simple and serviceable.
CHART
Fire Pump Power Path
ComponentDescription
Service/Source→ Fire Pump Controller (listed)
Controller→ Fire Pump (motor)
Power SourcesNormal + Alternate Source (as required)
ProtectionOCPD/Feeder arranged so pump keeps running
Keep OCPD/feeder choices aligned with reliability over convenience.
Fire pump controller
Labeling and source arrangement matter.
Service tap to fire pump
Follow 695 tap and OCPD specifics.

Chapter 6 — Field Quick Hits

Signs

Dedicated circuit + local disconnect.

Elevators

Lockable disconnect; separate lighting vs power.

EVSE

Continuous load — size at 125%.

Pools

Bond that deck. Expect GFCI.

PV

Rapid shutdown + labels.

Fire Pumps

Reliability beats convenience.

Knowledge Check

Answer all questions, then click Submit Answers. You’ll see your score after submitting. Nothing is graded until then.

1

Art. 600: A new storefront sign is being installed. What’s the correct branch-circuit approach?

2

Art. 620: Which is TRUE about elevator equipment circuits?

3

Art. 625: For EVSE, branch-circuit sizing typically uses:

4

Art. 630: Welder circuits are sized using:

5

Art. 640: One concern in audio racks is:

6

Art. 645: IT rooms using 645 rules typically provide:

7

Art. 680: What’s commonly required on pool pump motors?

8

Art. 680: The pool deck’s equipotential grid is primarily about:

9

Art. 690: PV output circuit ampacity is usually calculated at:

10

Art. 690: Rapid shutdown requirements primarily exist to:

11

Art. 691: Large-scale PV is different from 690 mainly because:

12

Art. 695: Fire pump power paths are arranged to prioritize:

13

Art. 600: Which is required for signs/outline lighting?

14

Art. 625: EVSE on a 40A nameplate should be on what size OCPD?

15

Art. 630: What commonly trips people up when sizing welder circuits?